ATTLEBORO RIVERFRONT DR. PH. II

Project Date: October 2014 - June 2017
Contract Value: $4,688,605.00
General Contractor
Project Scope:

The work to be done under this contract consists of construction of Riverfront Drive and a multi-use path and park between Wall Street and Olive Street on the site of the former Attleboro Public Works Department’s (PWD) yard. The project includes, but is not limited to earthwork, erosion control, roadway, concrete sidewalk, granite curbing, asphalt and concrete pavements, stormwater management system, sanitary sewer and utility systems, sewer main river crossing, brick pavers on concrete base, porous asphalt pavement, invasive species control, riverbank restoration, stockpiling and disposal of landfill/contaminated soils, landscaping, park amenities, lighting, signage, and pavement markings.